Peninsular Residences September Construction Update

Construction at Peninsula Residences has progressed on schedule through the month of August, with minmal inclement weather.

With the tower crane installed, the level 1 structure has been completed and the plan is to pour the Level 2 next week.

A key milestone towards the end of September will be the completion of the transfer slab (Level 2 to Level 3), where the car parking structure converts to residential levels.  Builders are aiming to pour this slab in early October at which point structural work is expected to speed up due to the regularity of the slab designs up the building.

Anticipated completion date is September - October 2019.

   

   

GET IN TOUCH
To find out more about the construction progress of Peninsula Residences in Surfers Paradise or if you have any queries relating to the settlement process, please do not hesitate to get in touch with our iBuyNew team today.
 
Call us on 1300 123 463.
 
Published on 20th of November 2018 by Marty Stanowich
Marty Stanowich
Marty Stanowich

DID YOU LIKE THIS ARTICLE?

Sign up to the iBuyNew newsletter to receive more article and property news straight to your inbox

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

RELATED ARTICLES