Peninsular Residences November 2018 Construction Update

Construction has progressed well at Peninsular Residences in Surfers Paradise over the past month and will be continue up until the Christmas shutdown period on the 21st December.  Workers will return on 7th January to recommence construction activities.

A milestone has been reached over the past month with the commencement of apartment fit-outs.  Current activities include:

Ground and Level 1 - Hydraulic and electrical services currently being installed.
Level 2 - Ceiling and Partitions have commenced as well as plumbing and electrical rough-in.
Level 3 - Back propping remains in place while the Level 4 slab is prepared and poured.
Level 4 - Structural slab reinforcing currently being laid with a scheduled concrete pour on 23rd November.
Two further pours will be targeted this year which will see the completion of the Level 6 structure.



GET IN TOUCH
To find out more about the construction progress of Peninsular Residences in Surfers Paradise or if you have any queries relating to the settlement process, please do not hesitate to get in touch with our iBuyNew team today.
 
Call us on 1300 123 463.
Published on 6th of December 2018 by Marty Stanowich
Marty Stanowich
Marty Stanowich

DID YOU LIKE THIS ARTICLE?

Sign up to the iBuyNew newsletter to receive more article and property news straight to your inbox

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

RELATED ARTICLES