Construction has progressed well at Panorama, Bowen Hills. Builders have now established their operations on site and completed surgace clearing of the development.
Rock breaking excavation will commence on Monday November 19 and will continue through to mid-December.
Foundation and footing construction associated with building of the basement is scheduled to commence prior to Christmas.
Crane towers are scheduled to be assembled on site by late January 2019.
It is forecast that the basement works at Panorama will be completed by early March 2019 and development will start to rise from the ground level from late March 2019.
Once construction reaches the podium level of the development, a new residential level is forecast to be constructed every 7 to 10 days.