Panorama Construction Update

Construction has progressed well at Panorama, Bowen Hills.  Builders have now established their operations on site and completed surgace clearing of the development.

Rock breaking excavation will commence on Monday November 19 and will continue through to mid-December.

Foundation and footing construction associated with building of the basement is scheduled to commence prior to Christmas.

Crane towers are scheduled to be assembled on site by late January 2019.

It is forecast that the basement works at Panorama will be completed by early March 2019 and development will start to rise from the ground level from late March 2019.
 
Once construction reaches the podium level of the development, a new residential level is forecast to be constructed every 7 to 10 days.



GET IN TOUCH
To find out more about the construction progress of Panorama in Bowen Hills or if you have any queries relating to the settlement process, please do not hesitate to get in touch with our iBuyNew team today.
 
Call us on 1300 123 463.
 
Published on 20th of November 2018 by Marty Stanowich
Marty Stanowich
Marty Stanowich

DID YOU LIKE THIS ARTICLE?

Sign up to the iBuyNew newsletter to receive more article and property news straight to your inbox

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

RELATED ARTICLES